Identifying, communicating, and managing project risks requires a risk management culture. This culture is defined by the values in which we operate.

Project Risk Management Objectives

 

The Project Risk Management is designed to:

 Be scalable to project size and complexity

 Pull communication of risks across project milestones and phases

 Actively manage risk to enhance project success

 Integrate into the current project delivery process, and

 Involve all functional units in the management of risks.

 

Project Risk Management Values

 

Identifying, communicating, and managing project risks requires a risk management culture. This

culture is defined by the values in which we operate. The following attributes depict PRM values

required for the development of a successful risk management culture. (Project Risk Management Handbook: A Scalable Approach, 2012)

 Risk decision‐making based on balancing project values such as cost, schedule, and quality

 Stewardship

 Efficiency

 Teamwork

 Joint ownership of risks and responsibilities

 Accountability

 

Benefits of Project Risk Management to the Project Team

 

Caltrans project risk management helps the project manager and the other project members to manage

project risks over the life of each project, enlisting the support and effort of all of the functional units as

the project moves along the delivery cycle. This includes: (Project Risk Management Handbook: A Scalable Approach, 2012)

 Better ability for the project team to focus time and effort on highest rated risks

 A scalable approach, consistent with existing processes

 Enhanced coordination and transparency with functional units, which facilitates early

identification of critical risks

 Bridging of functional stovepipes to maintain focus on project success by all functional units

 Support of the project manager’s mission through the management accountability process

 

What is meant by “Risk”

In the context of a project, we are concerned about potential impacts on project objectives such as cost and time. A general definition of “risk” in this context is: Risk is an uncertainty that matters; it can affect project objectives negatively or positively. The uncertainty may be about a future event that may or may not happen and the unknown magnitude of the impact on project objectives if it does happen. Thus, a “risk” is characterized by its probability of occurrence and its uncertain impact on project objectives.

The kinds of risks appearing in a risk register are shown below based on when they might occur during the life cycle of a project. (Project Risk Management Handbook: A Scalable Approach, 2012)

  • Throughout the project life cycle, a future event that may occur at any time in a project’s lifecycle is a risk. It has a probability of occurrence and an uncertain impact if it does occur.
  • During Planning and Design, uncertainty in the total cost estimate, due to uncertain quantities and unit prices is a risk. In this case the probability is 100% (the estimate and its uncertainties exist), and the uncertainties impact the project cost.
  • During construction, a Notice of Potential Claim (NOPC) has a probability of becoming a Contract Change Order (CCO) and an uncertain cost/time impact if this happens. This risk is retired from the register if the claim is dismissed or if it is replaced by a CCO.
  • During construction, a CCO which has occurred (100% probability) is a risk, but its cost/time

impact may be uncertain. If there is an estimate in the CCO Log of the project, the uncertainty is

expressed as a range around the estimate. This risk is retired from the register when the CCO is

executed with the contractor

 

Risk Identification

Risk identification determines what might happen that could affect the objectives of the project and how those things might happen. It produces a deliverable — the project risk register – that documents the risks and their characteristics. The risk register is subsequently amended by the qualitative or quantitative risk analysis, risk response, and risk monitoring processes. Risk identification is an iterative process because new risks may become known as the project progresses through its life cycle. (Project Risk Management Handbook: A Scalable Approach, 2012)

“Risk” Includes Threats and Opportunities

 

The concept of risk can include positive and negative impacts. This means that the word “risk” can be used to describe uncertainties that, if they occurred, would have a negative or harmful effect. The same word can also describe uncertainties that, if they occurred, would be helpful. In short, there are two sides to risk: threats and opportunities. Projects in design have the greatest potential for opportunities because the project is still open to changes. Risk reduction and avoidance are opportunities, as are value analyses, constructability reviews, and innovations in design, construction methods, and materials. Once a project enters construction, the project objectives (scope, time, and cost) are fixed contractually, so opportunities to save money and time are fewer. Any changes must be made using a contract change order (CCO), and only a negative CCO such as one resulting from a Value Engineering Change Proposal by the contractor would still afford an opportunity to save money and time. Otherwise, CCOs add cost and/or time to the project. So, the risk management focus during construction is on reducing or eliminating risks. (Project Risk Management Handbook: A Scalable Approach, 2012)

 

Qualitative Risk Analysis

Qualitative risk analysis includes methods for prioritizing the identified risks for further action, such as risk response. The PRMT can improve the project’s performance effectively by focusing on high‐priority risks. Team members revisit qualitative risk analysis during the project’s lifecycle. When the team repeats qualitative analysis for individual risks, trends may emerge in the results. These trends can indicate the need for more or less risk management action on particular risks or even show whether a risk mitigation plan is working. (Project Risk Management Handbook: A Scalable Approach, 2012)

 

 

 

Project Risk Management Handbook: A Scalable Approach. (2012) (1st ed.).


ANSWER.

PAPER DETAILS
Academic LevelCollege (3-4 years: Junior, Senior)
Subject AreaBusiness Studies
Paper Type Coursework
Number of Pages3 Page(s)/825 words
Sources3
Paper FormatMLA
SpacingDouble spaced

Loader Loading...
EAD Logo Taking too long?
Reload Reload document
| Open Open in new tab

 

https://termpapersmarket.com/wp-content/uploads/2018/11/tpm-01.png

×